This multi-dimensional project included many different aspects such as pond, trunk and outfall construction. The riverbanks were properly graded and restored with vegetation to provide new homes for wildlife living in the Grasslands. Additionally, rip rap was installed to reduce riverbank erosion. Specific scopes of work included:
- 75 meters of 1050mm Concrete Pipe
- 780 meters of 1500mm Concrete Pipe
- 20 meters of 1800mm Concrete Pipe
- Average Depth 7 – 9 Meters
- Pond Excavation – 215,000 Cubic Meters of Dirt
- Complete Riverbank Restoration Including 3,000 Plants