Avenue C Water Main and Roadway Improvements
Avenue C & 39th Street Rehabilitation
Saskatoon, Saskatchewan
This multi dimensional project utilized many techniques such as open cut trench box installation, trenchless horizontal directional drill installation and surface cathodic installation. Due to existing underground infrastructure restrictions, preconstruction planning allowed Hamm to maximize efficiency through city specific staging. Specific scopes of work included:
- Replaced 338 meters of 150mm-200mm PVC watermain
- 91 meter 8″ Horizontal Directional Drill constructed with terrabrute restrained PVC watermain
- 43 services reconnected to the new infrastructure
- Cathodic protection installation